Which of the following is NOT a component of contract administration?

Study for the Federal Acquisition Certification in Contracting Exam. Gain confidence with multiple choice questions that include hints and explanations. Prepare effectively and boost your exam readiness!

Drafting initial proposals is not a component of contract administration because this phase occurs prior to the execution of a contract. Contract administration focuses on the processes that happen after a contract has been awarded.

Components of contract administration include activities that ensure the contractor complies with the terms and conditions of the contract, such as tracking cost data to monitor expenditures against the budget, managing changes to the contract to accommodate any modifications or unexpected issues, and ensuring that the contractor receives timely payments for their work as stipulated in the agreement. Each of these activities is crucial for maintaining contract integrity and ensuring successful project outcomes, while drafting proposals is part of the pre-award phase, related to how the contract is initiated and negotiated, rather than how it is managed afterwards.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy